8 Aug 2011: Started on site
9 Aug 2011: Site scrape
10 Aug 2011: Power & phone lead in installed
15 Aug 2011: Water tank & HSTP installed
17 Aug 2011: Footings poured
19 Aug 2011: External Plumbing installed
22 Aug 2011: Pad smoothed
24 Aug 2011: Slab boxed
26 Aug 2011: Slab poured
29 Aug 2011: Framing started
1 Sep 2011: Roof trusses installed
13 Sep 2011: Colorbond roof installed with anticon blanket
19 Sep 2011: Windows & Sliding doors installed
20 Sep 2011: Electrical & Plumbing first fix including PV & Solar HWS
20 Sep 2011: Building wrapped
26 Sep 2011: Brick work started
28 Sep 2011: Plastering started
3 Oct 2011: Skirting & Architrave started
18 Oct 2011: Joinery Installed & Wet area tiles started