8 Aug 2011: Started on site
9 Aug 2011: Site scrape
10 Aug 2011: Power & phone lead in installed
15 Aug 2011: Water tank & HSTP installed
17 Aug 2011: Footings poured
19 Aug 2011: External Plumbing installed
22 Aug 2011: Pad smoothed
24 Aug 2011: Slab boxed
26 Aug 2011: Slab poured
29 Aug 2011: Framing started
1 Sep 2011: Roof trusses installed
13 Sep 2011: Colorbond roof installed with anticon blanket
19 Sep 2011: Windows & Sliding doors installed
20 Sep 2011: Electrical & Plumbing first fix including PV & Solar HWS
20 Sep 2011: Building wrapped
26 Sep 2011: Brick work started
28 Sep 2011: Plastering started
3 Oct 2011: Skirting & Architrave started
18 Oct 2011: Joinery Installed & Wet area tiles started
The majority of engagement party invitations went to the post on Monday, but a few stragglers went out today, so make sure you check your letter boxes. Or maybe your neighbors’. Please remember to RSVP by the 15th so we can make sure we have enough food for everyone. We’ll update the Gift Ideas page [...]
Engagement party invitations have come back from the printer and names will be added to them tonight. So check your letterbox for one of these: The engagement party will be held on the 25th November starting at 5:00pm. Dinner and drinks will be provided. Check out the Gift Ideas page.
Invitations for the engagement party have been sent to the publisher, hopefully they will only take a couple of days, so we can send them out by the start of November.