8 Aug 2011: Started on site
9 Aug 2011: Site scrape
10 Aug 2011: Power & phone lead in installed
15 Aug 2011: Water tank & HSTP installed
17 Aug 2011: Footings poured
19 Aug 2011: External Plumbing installed
22 Aug 2011: Pad smoothed
24 Aug 2011: Slab boxed
26 Aug 2011: Slab poured
29 Aug 2011: Framing started
1 Sep 2011: Roof trusses installed
13 Sep 2011: Colorbond roof installed with anticon blanket
19 Sep 2011: Windows & Sliding doors installed
20 Sep 2011: Electrical & Plumbing first fix including PV & Solar HWS
20 Sep 2011: Building wrapped
26 Sep 2011: Brick work started
28 Sep 2011: Plastering started
3 Oct 2011: Skirting & Architrave started
18 Oct 2011: Joinery Installed & Wet area tiles started
After all the running around for Ecovidual, we decided to get away for a few days down to Byron Bay. We stayed at the Bamboo Cottage, which is just a few minutes walk from town, they’re dog friendly, so we took Ralphie with us for his first trip to the beach. He loved it so [...]
Some more pictures of Ralphie from the weekend.
In a couple of weeks the Burgess Clan will grow to 5! Ralph will be coming to live with us as soon as we’ve built a fence and somewhere for him to sleep. Hopefully the 2 other boys don’t give him too much of a hard time. Come to think of it, the cats sleep [...]
We’ve got the wedding photo album back, if you want to see it drop us a line and well arrange a viewing. Now I just have to work out what to do with this website.
It’s taken a while but the kitchen is nearly complete! More picture to come once we finish it off.